Tan Hung Industrial Park – Bac Giang was approved to be included in the province’s industrial park development plan by the Prime Minister in Official Letter No. 216/TTg-CN on February 23, 2021.
The Bac Giang Provincial People’s Committee approved Decision No. 715/QD-UBND, approving the detailed construction plan of Tan Hung Industrial Park at a 1/500 scale on July 16, 2021.
On November 23, 2021, the investment project for infrastructure construction and operation of Tan Hung Industrial Park was approved by the Prime Minister in Decision No. 1971/QD-TTg, with infrastructure investment by Lideco 1 Joint Stock Company.
The total investment capital for the Tan Hung Industrial Park project is 1.185 billion VND, with an operational period of 50 years (2021-2071).
The industrial park covers a total area of 105,3 hectares, with industrial land accounting for 73,61 hectares (approximately 69,91% of the planned area), divided into two phases:
| 租金 | 土地租金 $130/平方米 |
|---|---|
| 其他费用 | Land rental price 30 USD/m2 for the entire project operation period. The rental price may vary depending on the area and location of the leased land |
| The fee for infrastructure management and maintenance 0,5 USD/m2/year | |
| Land lease payment The lessee leases the land for 50 years with a one-time payment, and the infrastructure usage fee already includes the land lease payment | |
| Electricity price Applied according to EVN’s electricity tariff. Reference prices: Peak hours: 0,12 USD/KWh. Normal hours: 0,064 USD/KWh. Off-peak hours: 0,042 USD/KWh (excluding VAT). | |
| Water price 0,57 USD VND/m3, calculated based on actual water usage | |
| Wastewater treatment fee 0,4 USD/m3 (excluding VAT).The calculation of the treated wastewater fee is based on 80% of the clean water input. | |
| Telephone, fax, and other expenses Based on the rates provided by the service providers |